Traffic Update

 

Projects affecting San Marcos traffic for week of May 13 - May 19, 2012
Online: sanmarcostx.gov/traffic

NORTH LBJ: 1000 block, southbound lane of traffic will be closed May 14 and/or May 15, 2012 from 9 a.m. - 4 p.m. for geotechnical sampling. Fugro Consultants, 512.903.8143.

NORTH LBJ: 1300 block, geotechnical sampling along the northbound lane of traffic on May 14 and/or May 15, 2012 from 9 a.m. - 4 p.m. Fugro Consultants, 512.903.8143.

NORTH LBJ: 100 block, all lanes of traffic will be closed May 19, 2012 from 7 a.m. - 6:30 p.m. for the Texas Natural & Western Swing Festival. Main Street Program, 393.8430.

EAST SAN ANTONIO STREET: 100 block, all lanes of traffic will be closed May 19, 2012 from 7 a.m. - 6:30 p.m. for the Texas Natural & Western Swing Festival. Main Street Program, 393.8430.

MILL STREET: From Aquarena Springs Drive to Uhland Road will have intermittent lane closures from May 14 to June 14, 2012 for asphalt overlay. Public Services - Transportation, 393.8036.

IH 35 NORTH BOUND: From Blanco River Bridge to Yarrington Overpass. The middle and outside lanes will be closed from May 14 - May 16 (9:00 p.m. to 5:00 a.m.) for mill and inlay hot mix. Texas Department of Transportation, 353-1061

EAST MCCARTY LANE: Landscape and maintenance crews will be operating along the project limits. Anticipate occasional lane closures, slow moving vehicles in lanes, construction equipment in roadside and interrupted use of sidewalks during watering and/or landscaping operations until mid May. Capital Improvements, 393.8130.

RIVERSIDE DRIVE: The City has begun a 90-day trial period for 25 MPH signs between Hopkins Street and the IH-35 southbound frontage road. Please submit your comments to the Public Services Transportation Division at 393.8036.

EAST SAN ANTONIO STREET: Half a block closed from alley to N. LBJ every Saturday from 8 a.m. - 3 p.m. for the Farmers Market on the Square. Main Street Program, 393.8430.

RIO VISTA TERRACE NEIGHBORHOOD INFRASTRUCTURE PROJECT

CHEATHAM STREET AT RIVERSIDE DRIVE: Will be closed for installation of storm drains until May 25, 2012. Capital Improvements, 393.8130.

LONG TERM ROAD CLOSURES:

UNIVERSITY DRIVE: North sidewalk closure between Moon Street and LBJ until November 1, 2012. Hunt Construction Group, Inc., 512.245.2068.

FREDERICKSBURG: 400 block, all lanes of traffic for half the block will be closed from March 8, 2012 to September 1, 2013 for construction of apartment complex. Skyline Commercial, Inc., 512.343.4555.

NORTH EDWARD GARY STREET: 400 - 500 block, from University Drive to Woods Street will be closed for construction of the new Performing Arts Center Complex. Scheduled completion date is November 2013. Texas State University, 245.1547.

MOON STREET: West sidewalk closure from University Drive to Concho Green until September 2013. Texas State University, 245.2244.